Activity-Based Costing
6 worked questions on activity-based costing, taken from the 144 in the UniMCQs bank. Each one shows the correct option and the reasoning behind it, so you can check your own working rather than just your answer.
Question 1
In an activity-based costing system, what is a cost driver?
- aThe manager responsible for controlling an overhead
- bThe total overhead of a production department
- cThe direct material used by one unit of product
- The factor that causes the cost of an activity to change
A cost driver is the activity measure that causes an activity's cost to be incurred, such as the number of set-ups for set-up costs or the number of purchase orders for ordering costs.
Question 2
A company pools €45,000 of inspection overhead, driven by production runs. It budgets 60 production runs in total. What is the cost driver rate for inspections?
- a€450 per production run
- b€600 per production run
- c€1,500 per production run
- €750 per production run
€45,000 ÷ 60 production runs = €750 per run.
Question 3
A machine set-up cost pool holds €642,960 and 190 set-ups are budgeted. What is the cost driver rate?
- a€2,450 per set-up
- b€3,195 per set-up
- c€3,250 per set-up
- €3,384 per set-up
€642,960 ÷ 190 set-ups = €3,384 per set-up.
Question 4
What is a volume-based cost driver?
- A driver under which consumption of overhead is directly related to the number of units produced
- bA driver measured in euro rather than in physical units
- cA driver used only for facility-sustaining costs
- dA driver that changes with the number of batches rather than units
Volume-based drivers apply to activities performed each time a unit is made, so overhead consumption rises and falls with output.
Question 5
What is the first step in designing an activity-based costing system?
- Identify the major activities that take place in the organisation
- bDetermine the cost driver for each major activity
- cAssign the cost of activities to products
- dCalculate a plant-wide overhead absorption rate
The design runs identify activities, assign costs to a pool for each activity, determine the driver for each activity, then assign activity costs to products.
Question 6
A machine set-up activity is charged with €600,000 and 12,000 set-up hours are worked. What is its cost driver rate?
- €50 per set-up hour
- b€60 per set-up hour
- c€120 per set-up hour
- d€500 per set-up hour
€600,000 divided by 12,000 set-up hours gives €50 per set-up hour.
The other 144 are inside.
Sign up and you get the whole topic, one question at a time, marked the instant you submit, with a breakdown of where your marks went.
Free to try. No card required.
More management accounting topics
- Absorbing Overheads
- Absorption and Variable Costing
- Accounting and Management Information Systems
- Accounting Entries for a Job Costing System
- Budgeting and Variances
- Contemporary Technologies and Data Analytics
- Cost Accumulation for Inventory Valuation and Profit Measurement
- Cost Assignment: Cost Objects and Allocation Bases
- Cost Classification and Behaviour
- Cost-Volume-Profit Analysis
- Financial Accounting Compared with Management Accounting
- Job and Batch Costing
- Labour Costs: Idle Time and Overtime
- Presenting Information
- Reallocating Service Department Costs
- Relevant Information for Decisions
- Service Costing and Process Costing
- Sources of Data
- Traditional Costing: The Two-Stage Allocation Process