  1. Question 1

    Costing systems are conventionally divided into which two broad families?

    • aAbsorption costing and marginal costing
    • bHistorical costing and standard costing
    • Specific order costing and continuous operation costing
    • dDirect costing and indirect costing

    Specific order costing collects costs for separately identifiable orders; continuous operation costing averages costs over the units produced in a period.

  2. Question 2

    Which document does the purchasing department send to an outside supplier?

    • Purchase order
    • bPurchase requisition
    • cMaterials requisition note
    • dGoods received note

    The purchase order is the external document that commits the business to buy the goods on the terms stated.

  3. Question 3

    Direct materials drawn for a job prove surplus and are returned to stores. What is the double entry?

    • aDebit work in progress, credit stores ledger control
    • Debit stores ledger control, credit work in progress
    • cDebit creditors, credit stores ledger control
    • dDebit production overhead control, credit work in progress

    The issue is reversed: the cost comes off work in progress and the materials go back into the stores asset.

  4. Question 4

    A job has direct materials of €10,000, direct labour of €6,000 in machining and €8,000 in assembly, and absorbed overhead of €6,000 in machining and €8,000 in assembly. What is the total cost of the job?

    • a€24,000
    • b€28,000
    • c€30,000
    • €38,000

    €10,000 materials + €14,000 labour + €14,000 absorbed overhead = €38,000.

  5. Question 5

    Direct operatives spend part of the week repairing machinery rather than working on jobs. How is the cost of those hours treated?

    • aCharged to work in progress, because the operatives are direct workers
    • bCharged to the customer whose job was delayed
    • cLeft in the wages control account as a balance
    • Charged to production overhead, because the hours cannot be traced to a job

    The classification follows the work done, not the worker. Time not spent on an identifiable job is indirect.

  6. Question 6

    How is non-manufacturing overhead, such as administration and selling costs, treated in a job costing system?

    • aAbsorbed into jobs using a machine hour rate
    • bAdded to the stores ledger control account
    • cCarried forward in finished goods inventory
    • Charged directly against profit for the period rather than absorbed into jobs

    Only production overhead is absorbed into the cost of jobs. Administration and selling costs are period costs written off as incurred.