Question 1
In target costing, how is the target cost of a product determined?
- Target price less target profit
- bTarget price less estimated production cost
- cEstimated production cost plus a required profit mark-up
- dEstimated production cost less the cost gap
Target cost equals the market-driven target price minus the target profit. It is the highest acceptable cost of the product.
Question 2
A manufacturer has identified a cost gap on a new product under target costing. Which of the following is NOT an acceptable way to close the gap?
- aIncreasing automation by introducing machinery
- bFinding an alternative, cheaper material without compromising quality
- Increasing the selling price of the product
- dConsidering an alternative product design
Under target costing the gap cannot be closed by increasing the selling price or reducing the profit. The gap must be closed through cost reductions that do not impair quality.
Question 3
A company is introducing activity-based costing. It has formed a cost pool for quality inspection costs. Which cost driver is most appropriate for this pool?
- aNumber of machine hours
- Number of inspections
- cPrime cost per unit
- dNumber of units produced
Under ABC, each cost pool is linked to the factor that drives it. Inspection costs are driven by the number of inspections performed.
Question 4
At which stage of a product's life cycle are decommissioning and product retirement costs expected to be at their highest?
- Decline
- bGrowth
- cIntroduction
- dMaturity
Decommissioning and product retirement costs are at their highest in the decline stage, when the product is being withdrawn.
Question 5
A product sells for €150 per unit, has a direct material cost of €60 per unit, and needs 2 hours on the bottleneck resource. Total factory cost is €900,000, and 30,000 hours are available on the bottleneck. What is the product's throughput accounting ratio?
- a0.67
- b2.5
- 1.5
- d3.0
Return per factory hour = (€150 − €60) ÷ 2 = €45. Cost per factory hour = €900,000 ÷ 30,000 = €30. The ratio is €45 ÷ €30 = 1.5.
Question 6
Under the theory of constraints, a factory finds that work in progress keeps building up in front of its bottleneck machine. Which step in the theory of constraints process deals directly with this problem?
- aRank products by throughput per bottleneck hour
- Ensure production up to the bottleneck runs at the same rate as production after the bottleneck
- cIdentify the bottleneck or constraint
- dElevate the bottleneck by finding ways to increase its output
Work in progress builds up when output before the bottleneck exceeds what the bottleneck can handle, so the step that matches production up to the bottleneck with production after it prevents this build-up.