Decision-Making Techniques (Part 2)

6 worked questions on decision-making techniques (part 2), taken from the 15 in the UniMCQs bank. Each one shows the correct option and the reasoning behind it, so you can check your own working rather than just your answer.

  1. Question 1

    A company sells a single product for €20 per unit. The variable cost is €12 per unit, and fixed costs are €60,000 per year. What is the break-even sales volume in units?

    • 7,500 units
    • b3,000 units
    • c5,000 units
    • d150,000 units

    Contribution per unit is €20 − €12 = €8, so break-even volume is €60,000 ÷ €8 = 7,500 units.

  2. Question 2

    Which of the following is an assumption underlying cost-volume-profit (CVP) analysis?

    • aFixed costs may rise in steps as output increases
    • bSelling prices fall as sales volume rises, reflecting the price-demand relationship
    • Everything produced is sold, so inventory levels do not change
    • dSemi-variable costs are included without being split into fixed and variable elements

    CVP analysis assumes that whatever is produced is sold, so inventory levels do not change. It also assumes there are no stepped fixed costs, no price-demand effects and no unsplit semi-variable costs.

  3. Question 3

    A company is pricing a one-off contract. It would incur €6,000 of extra labour, €5,000 of materials bought specifically for the contract and €2,000 of additional fixed costs specific to the contract. A feasibility study already completed cost €1,500. The contract would also be apportioned €3,000 of existing general overheads. What is the minimum price the company should accept?

    • a€14,500
    • €13,000
    • c€16,000
    • d€11,000

    The minimum price is the total of future incremental cash flows: €6,000 + €5,000 + €2,000 = €13,000. The €1,500 study is a sunk cost, and the €3,000 apportioned overhead does not change because of the contract, so neither is included.

  4. Question 4

    How does risk differ from uncertainty in decision making?

    • aRisk and uncertainty are the same thing and the terms are interchangeable
    • bRisk applies only to company-specific factors, whereas uncertainty applies only to market-wide factors
    • cRisk involves unknown possibilities, whereas uncertainty involves known probabilities
    • Risk involves known possibilities with known or estimable probabilities, whereas with uncertainty the probabilities and/or some possibilities are unknown

    Risk is quantifiable, with known possibilities and known or estimable probabilities. Under uncertainty, the probabilities and/or some of the possibilities are unknown.

  5. Question 5

    A new product line has budgeted sales of €5,000, variable costs of €3,000 and fixed costs of €1,500, giving a profit of €500. By what percentage would sales volume have to fall to eliminate the profit?

    • a33.3%
    • b16.7%
    • 25%
    • d10%

    A fall in sales volume reduces contribution. Contribution is €5,000 − €3,000 = €2,000, so sensitivity = €500 ÷ €2,000 = 25%.

  6. Question 6

    A company sells a single product for €25 per unit. The variable cost is €15 per unit and fixed costs are €40,000 per year. Budgeted sales are 5,000 units. What is the margin of safety as a percentage of budgeted sales volume?

    • 20%
    • b80%
    • c25%
    • d40%

    Break-even volume is €40,000 ÷ (€25 − €15) = 4,000 units, so the margin of safety is 5,000 − 4,000 = 1,000 units. As a percentage of budgeted sales, this is 1,000 ÷ 5,000 × 100% = 20%.

The other 15 are inside.